The Municipality of Concordia, through the Secretariat of Urban Development, continues today, Wednesday, May 15, with the program for the repair of unpaved streets as well as pothole patching and cleaning of drains in different sectors and neighborhoods of the city.
The sectors where work will be carried out during the day are as follows:
Parque Río Uruguay Neighborhood: Grading of Néstor Garat, Mayor Quinteros, Echagüe, Brasil, and Victorino Simón streets.
Las Tejas Neighborhood: Repair of Blas Parera street between Santísima Trinidad and San Antonio.
Norte Neighborhood: Grading and repair of Federación street between Presidente Illia and Teniente Ibáñez.
San Pantaleón Neighborhood: España street between Humberto Primo and Federación.
Grading and repair of Vuelta del Hipódromo, J.J. Valle and Fátima streets; De Los Viñedos between Paula Albarracín and Nogoyá.
Concrete pouring at: Sargento Cabral between Laprida and Alvear; Velez Sarsfield past Sarmiento; San Martin between Laprida and Alvear.
Asphalt pouring at: Intersection of Moulins and Tavella towards the east; Moulins near Laprida; Tavella between Teniente Ibáñez and Moulins; Carriego near Entre Ríos; Entre Ríos near Andrade; La Rioja between Catamarca and Corrientes.
Opening and compaction of concrete potholes at: Espejo and Presbítero del Castillo; Rivadavia between Coldaroli and Liniers; Lamadrid past Montevideo; DP Garat reaching Catamarca.
Construction of a gutter at Chabrillón and the river.
The sectors where work will be carried out during the day are as follows:
Parque Río Uruguay Neighborhood: Grading of Néstor Garat, Mayor Quinteros, Echagüe, Brasil, and Victorino Simón streets.
Las Tejas Neighborhood: Repair of Blas Parera street between Santísima Trinidad and San Antonio.
Norte Neighborhood: Grading and repair of Federación street between Presidente Illia and Teniente Ibáñez.
San Pantaleón Neighborhood: España street between Humberto Primo and Federación.
Grading and repair of Vuelta del Hipódromo, J.J. Valle and Fátima streets; De Los Viñedos between Paula Albarracín and Nogoyá.
Concrete pouring at: Sargento Cabral between Laprida and Alvear; Velez Sarsfield past Sarmiento; San Martin between Laprida and Alvear.
Asphalt pouring at: Intersection of Moulins and Tavella towards the east; Moulins near Laprida; Tavella between Teniente Ibáñez and Moulins; Carriego near Entre Ríos; Entre Ríos near Andrade; La Rioja between Catamarca and Corrientes.
Opening and compaction of concrete potholes at: Espejo and Presbítero del Castillo; Rivadavia between Coldaroli and Liniers; Lamadrid past Montevideo; DP Garat reaching Catamarca.
Construction of a gutter at Chabrillón and the river.