The Municipality of Concordia, through the Secretariat of Urban Development, continues today, Wednesday, July 31, with the program for the repair of unpaved streets as well as pothole patching and cleaning of drains in different sectors and neighborhoods of the city.
The sectors where work will be carried out during the day are as follows:
Pothole patching at Moulins and La Pampa; Sara Neira and Tavella.
Pancho Ramírez Neighborhood: Repair of Alda Norte and 53 streets.
17 de Octubre Neighborhood: Repair of Intendente Larocca East and West streets between Teniente Ibáñez and J.J. Sola. Continue along J.J. Sola between Paula Albarracín and Rivoli.
Parque Neighborhood: Repair continues on Gualeguay street between J.J. Valle and Lieberman and cross streets of República Argentina street.
Lavarden Neighborhood: Repair continues on Padres Capuchinos street, between Tavella and La Paz.
Agua Patito Neighborhood: Grading and repair of 11 de Noviembre, 59, 60 and other streets.
Nebel Neighborhood: Graveling continues on Victorino Simón and 6 de Caballería streets.
Gatto and Diamante streets site: Distribution of fill material
Opening and compaction: Concejal Veiga, between Ricardo Rojas and San Lorenzo.
Compaction on Nogoyá streets near Ricardo Rojas; Moulins and Humberto Primo; Gregoria Pérez and Boulevard Yuquerí.
Curb and gutter: Concrete pouring on Arruabarrena street, south orientation, between San Juan and La Rioja; on Poenitz street, north orientation, between San Juan and La Rioja.
Sawing of potholes on Perú and Avellaneda streets; Chile and Avellaneda; Perú and Ramírez; Chile and Ramírez; Aristóbulo del Valle, between Brown and Laprida; Aristóbulo del Valle at the 400 block.
The sectors where work will be carried out during the day are as follows:
Pothole patching at Moulins and La Pampa; Sara Neira and Tavella.
Pancho Ramírez Neighborhood: Repair of Alda Norte and 53 streets.
17 de Octubre Neighborhood: Repair of Intendente Larocca East and West streets between Teniente Ibáñez and J.J. Sola. Continue along J.J. Sola between Paula Albarracín and Rivoli.
Parque Neighborhood: Repair continues on Gualeguay street between J.J. Valle and Lieberman and cross streets of República Argentina street.
Lavarden Neighborhood: Repair continues on Padres Capuchinos street, between Tavella and La Paz.
Agua Patito Neighborhood: Grading and repair of 11 de Noviembre, 59, 60 and other streets.
Nebel Neighborhood: Graveling continues on Victorino Simón and 6 de Caballería streets.
Gatto and Diamante streets site: Distribution of fill material
Opening and compaction: Concejal Veiga, between Ricardo Rojas and San Lorenzo.
Compaction on Nogoyá streets near Ricardo Rojas; Moulins and Humberto Primo; Gregoria Pérez and Boulevard Yuquerí.
Curb and gutter: Concrete pouring on Arruabarrena street, south orientation, between San Juan and La Rioja; on Poenitz street, north orientation, between San Juan and La Rioja.
Sawing of potholes on Perú and Avellaneda streets; Chile and Avellaneda; Perú and Ramírez; Chile and Ramírez; Aristóbulo del Valle, between Brown and Laprida; Aristóbulo del Valle at the 400 block.